Building utilities

Chilled Water Plant

Building Information

The new combined heat and power (CHP) Central Plant is located in the southeast quadrant of the ASU at the Polytechnic campus and provides the necessary utilities to operate new buildings, which consists of classroom and office buildings, new research facilities, and future intended growth.

CHP Central Plant consists of:

  • 3-Cell Cooling Towers
  • Boiler Water Pumps
  • Chilled Water Pumps
  • Combustion turbine generators
  • Condenser Water Pumps
  • Deaerator for Steam Production
  • Gas Compressor Skid with Accessories
  • Generator Electrical Switching Equipment
  • Heat Recovery Steam Generators
  • Turbine Driven Chillers with Surface Condenser
Campus:Polytechnic
Gross Square Footage:5,442
Total Project Cost:$18,500,000
Architect:RSP
Construction Team:ASES
Project Start Date:May 2007
Project End Date:March 2008