Orange Mall

Phase 1 - East Section

149,402

(kWh)

Annual Production FY 2019

409

(kWh)

Average Daily Production FY 2019

15.46%

 

FY 2017 Capacity Factor FY 2019

$866

(dollars in thousands)

Total Project Cost

Phase 2 - West Section

195,216

(kWh)

Annual Production FY 2019

535

(kWh)

Average Daily Production FY 2019

16.15%

 

Capacity Factor FY 2019

$1.07

(dollars in millions)

Total Project Cost

The following information is the same for both phases. 

Campus: Tempe

Racking System: Custom steel structure

Address: Orange Mall between Cady Mall and Union Drive

System Type: 8-degree Fixed

Panel Model: JAP6-72

System Designer/Installer: Strategic Solar Energy, LLC

Panel Type: Polycrystalline

System Owner: Arizona State University owned

Panel Manufacturer: JA Solar Holdings Co., Ltd.

Contract Type: Arizona State University owned

Inverter Manufacturer: Advanced Energy Industries, Inc.

 

 

Phase 1 - East Section

Phase 2 - West Section

Peak DC Output: 137.88 kWdc

Peak DC Output: 172.44 kWdc

Annual Production FY 2019: 149,402 kWh 

Annual Production FY 2019: 195,216 kWh 

Average Daily Production FY 2019: 409 kWh

Average Daily Production FY 2019: 535 kWh

Capacity Factor FY 2019: 15.46%

Capacity Factor FY 2019: 16.15%

Commissioned Date: 12/2013

Commissioned Date: 12/2013

Number of Panels: 480

Number of Panels: 600

Panel Size: 264 at 285 Watts, 216 at 290 Watts

Panel Size: 320 at 285 Watts, 280 at 290 Watts   

Number of Inverters: 1

Number of Inverters: 2

Inverter AC Watt rating: 100

Inverter AC Watt rating: 1 at 50, 1 at 100

Inverter Model: AE100TX

Inverter Model: AE50TX, AE100TX

REC Incentive: $0.08/kWh (APS)

REC Incentive: $0.05/kWh (APS)

Total Project Cost: $866,000

Total Project Cost: $1,124,152