Section 3 – Permits required by other state and county agencies

ADEQ Approval for Water System Construction – Drinking Water Facilities 

Approval to construct or modify water systems

An approval must be obtained from ADEQ when a new facility or water system is to be constructed or an existing facility or system is to be modified and the modification affects the capacity, quality, flow, location or operational performance of the facility or system. To obtain approval:

  • Complete an Application for Approval to Construct.
  • Submit an Engineering Design Report, design drawings, specifications and other documentation for review.
  • Submit required application fees.

After review and approval of the application documentation, an Approval to Construct Certificate is issued to allow construction of the system.

Approval of construction or modification of water systems

The Approval of Construction will be issued when construction is complete prior to using systems after the following documents have been received and approved by ADEQ:

  • As Built Plans.
  • Domestic water pressure line test.
  • Domestic water quality test.
  • Engineers Certificate of Completion.
  • Sewer leakage and deflection tests.

For additional information, visit the ADEQ website.

AZPDES General Permit AZG2021-002 for Stormwater Discharges from MS4s

ASU owns and operates state-owned storm sewer systems which are similar to separate storm sewer systems in municipalities; therefore, it meets the definition of a Non-Traditional Small MS4. ASU is permitted under the Arizona Pollutant Discharge Elimination System General Permit AZG2021-002 for small Municipal Separate Storm Sewer Systems. The permittee has developed, implemented and maintained a construction activity stormwater runoff control program to minimize or eliminate pollutant discharges to the MS4 from construction activities that disturb one acre or more of land.

AZPDES Construction General Permit AZG2020-001 for Stormwater Discharge

ADEQ requires construction site operators to submit for coverage under the Arizona Pollutant Discharge Elimination System Construction General Permit AZG2020-001 for construction activities that include clearing, grading and excavating that result in land disturbance equal to or greater than one acre or disturbance of less than one acre of land if it is part of a larger common plan of development.

The objective of Construction General Permit AZG2020-001 is to reduce the transport of sediment and other pollutants from construction sites. ASU is different from traditional MS4s in that it is typically the owner of all construction projects within their MS4. ASU’s Capital Programs Management Group oversees all construction projects, maintains an inventory of projects under their management, and enforces AZPDES requirements. Projects are required to be designed and constructed according to ASU’s Project Guidelines. Stormwater Management Program implementation and enforcement is conducted through the construction contracting process.

To obtain coverage under Construction General Permit AZG2020-001:

  • The operator shall develop a Stormwater Pollution Prevention Plan before submitting the Notice of Intent for permit coverage and prior to conducting any construction activity.
  • The operator shall submit a complete and accurate AZPDES NOI form to ADEQ electronically via the myDEQ website.
  • The SWPPP shall be prepared and implemented in accordance with good engineering practices and shall:
    • Assure compliance with the terms and conditions of this permit; and identify the responsible person for on-site SWPPP implementation.
    • Identify all potential sources of pollution that may reasonably be expected to affect the quality of stormwater discharges from the construction site.
    • Identify, describe, and ensure implementation of control measures that will be used to reduce pollutants in stormwater discharges from the construction site.

Once ADEQ issues a Notice of Intent Certificate Authorization Number, the operator shall:

  • Provide a copy of the Authorization Certificate, Notice of Intent and SWPPP to CSS.
  • Maintain a copy of the Authorization Certificate and SWPPP at the construction site.
  • Maintain copies of Stormwater Inspection reports at the construction site.
  • Implement Best Management Practices outlined in the SWPPP before and during construction.

Stormwater inspections at construction sites

ASU’s Erosion, Sediment Control and Grading Policy describes the stormwater inspection and enforcement process. All university construction projects are inspected at four milestones: 

  1. Placement of erosion and sediment control measures.
  2. When sediment control measures are relocated or revised.
  3. Final grading complete.
  4. Final landscaping.

According to the policy, any construction work that is not approved must be corrected and re-inspected before construction may continue to the next stage. Enforcement mechanisms include Stop Work Order and revocation of the Building Permit. Final payment is withheld until the Final Inspection is successfully completed. ASU also maintains the right to report serious violations to ADEQ for prosecution and possible fines.

After the construction project is complete, the operator shall:

  • Submit a Notice of Termination to ADEQ within 30 days after final stabilization has been achieved.
  • Submit a copy of the ADEQ Notice of Termination Acknowledgement Letter to Construction Support Services.

The following activities do not require coverage under the AZPDES Permit AZG2020-001:

  • Construction activities unrelated to earth disturbing activities such as interior remodeling, completion of interiors of structures, etc.
  • Geotechnical, environmental, or archeological projects that collectively disturb less than one acre.
  • Re-paving roads if the sub-grade is undisturbed.
  • Routine earth disturbing activities that are part of the normal day-to-day operation of a completed facility – daily cover for landfills, maintenance of gravel roads or parking areas, landscape maintenance, etc.
  • Routine maintenance performed to maintain the original line and grade, hydraulic capacity or original purpose of the facility and that disturbs less than five acres. By definition, maintenance projects are expected to be short-term and involve minimal mass grading.

Find out more about ASU’s Stormwater Management Program.

Manufactured Housing Installation Plan Approval and Permit 

Double-wide manufactured housing installations require an Installation Plan Approval Application and a Permit approved by the State of Arizona. See additional details at the Arizona Department of Housing website. 

Maricopa County Dust Control Permit 

Dust-generating activities with a total disturbed soil surface area of one-tenth acre – 4,356 square feet or more – within Maricopa County is regulated by the Maricopa County Air Quality Department. Dust-generating activity requires a contractor to obtain a valid Dust Control Permit and implement a Dust Control Plan before commencing the dust generating activity. Subcontractors working for a contractor on a dust-generating activity must obtain a Maricopa County Registration Confirmation. Several examples of bare soil disturbance activities requiring a Dust Control Permit:

  • Areas of disturbance such as stockpiles, storage and equipment yards.
  • Construction activity.
  • Demolition of buildings.
  • Planting vegetation on bare soil.
  • Removing and replanting vegetation.

Dust Control Permit Requirements – not limited to this list:

  • An Asbestos/NESHAP notification is required for the demolition of structures.
  • Changes must be submitted to MCAQD: Permit Plan Change, Permit Acreage Increase Request, Permit Name Change Request, and Dust Control Coordinator Change Notification.
  • Construction Support Services must have a copy of the Maricopa County Air Quality Dust Control Permit and Dust Control Plan before an ASU Building Permit is issued.
  • Contractor must obtain a Dust Control Permit even if the sub-contractor has a Maricopa County Dust Control Registration Confirmation.
  • Dust Control Permit and Dust Control Plan must be posted at the construction site at all times.
  • Dust Control Permits are valid for one year from the date of approval. 
  • Permit Cancellation Request must be submitted to initiate closeout. Permit applicant remains responsible for violations for as long as the permit remains open.

For additional information, visit the Maricopa Air Quality Department website.

State Fire Marshal Permit

The Office of the State Fire Marshal has a policy agreement relinquishing all submittals to the ASU Fire Marshal's Office as of January 2010. All submittals to the ASU Fire Marshal's Office must follow State Fire Marshal submittal requirements and protocols. This is necessary to maintain separation of ASU Fire Marshal and State Fire Marshal functions. The ASU Fire Marshal's Office is obligated by policy agreement to conduct periodic review to ensure compliance.